Scope: ITW Military GSE requires that all suppliers furnish a first
article report when a fabricated product meets one of more
of the following criteria:
1.
Supplier is fabricating the product for the first time.
2. First Article is required per flow down requirements
noted on the Purchase Order
3. When the supplier has not produced the product for 12
months.
4. If the supplier has relocated their facility utilized to
produce the product.
5. A change in sub-tier suppliers has occurred.
6. Products are fabricated to a newly revised drawing.
Purpose: A The First Article Inspection (FA) report requirement defines
the information to be incorporated on to all FA reports submitted
for review for all products manufactured by an approved supplier.
Definitions:
Measured
results: The actual measurement of 100% of all features
and all notes on the drawing, this shall include
but is
not limited to special processes (weld requirements,
painting, plating, heat
treating etc) and dimensions listed as “TYP” and
or dimensions that are 2 places or more.
E.g.
a dimension on the print is listed as “Slot .37
Wide X 2.00 LG thru 2 pl” list on FA report the
same way.
Fabricated
part: Products that are manufactured to ITW Military
GSE’s
drawing requirements.
COTS
(Commercial off the shelf) Products that require a Certificate
of Compliance C of C) only, unless
otherwise specified on
the Purchase Order.
Procedure/Method: All FA reports require the following information on all pages
unless otherwise
indicated.
Part
name
Part number
Revision level
Purchase Order number
Part status (New, revised, recertified, reworked)
Suppliers/Customers name
Item number (number assigned to drawing feature
or note)
Dimension/Specification
Measurement results
Check off columns: Indicating if part in
or out of tolerance
Tolerance: Indicate as per drawing requirements
for each line item or if similar a note “All tolerances are +/- unless otherwise indicated” (page
one only)
Page number (1 of X)
NOTE: Revised parts that are classified, as a redesign will require
a new FA report.
The FA report shall be attached to a copy of the drawing,
with all item numbers on the FA report annotated on the
product drawing.
Alternative
FA reporting: A submitted FA may be submitted by annotating
the measured dimension directly onto the
drawing. Each measured
dimension shall
be placed
next to the corresponding drawing dimension.
All
FA reports shall be validated by the supplier with an appropriate
inspection stamp and/or a signature.
First